Resource Planning. Target: Based on the work expected, Ensure we have enough site resources of Engrs, Technicians and Helpers.
Lets Grow the business together. Capture "qualified" leads and earn Rs 100/- per lead.
Resource Planning. Target: Based on the work expected, Ensure we have enough site resources of Engrs, Technicians and Helpers.
For each confirmed order, estimate the number of engr days, supervisor days and helper days . A total of these will give you the total resource days required with us. As a thumbrule it should not exceed the number of total resources available with us for a months time. This is a indicator if we have to outsource some jobs.